RICHMOND, Va.--(BUSINESS WIRE)--Dominion Energy, Inc. (NYSE: D), today provided several updates for the Coastal Virginia Offshore Wind (CVOW) project. The 2.6 GW, fully permitted project is now ...
Steven D. Ridge, Executive Vice President and CFO, stated that the company "had another strong quarter of execution across each of these priorities," highlighting consistent achievement of financial ...
Dominion (D) Energy released the following statement in response to the U.S. Department of Interior’s Director’s Order for a 90-day suspension of work issued for the Coastal Virginia Offshore Wind ...
WASHINGTON, D.C. (December 22, 2025) – A group of public interest organizations involved in an ongoing lawsuit to stop construction of the massive Virginia offshore wind project are applauding the U.S ...
NORFOLK, Va. — A federal judge has ruled in favor of Dominion Energy, issuing a preliminary injunction in its case challenging the Trump administration's freezing of offshore wind projects. The ...
Dominion Energy said its 2.6-GW Coastal Virginia Offshore Wind (CVOW) project is more than 70% complete and remains on track to deliver its first power to the grid by March, even as executives ...
Dominion Energy has hit a major milestone in the construction of its Coastal Virginia Offshore Wind (CVOW) project. The company has put in place 78 monopile foundations and four offshore substation ...
The first jacket foundation for the substation of the Coastal Virginia Offshore Wind (CVOW) project has departed from the Danish Port of Esbjerg and is on its way to the United States to be installed ...
Port of Virginia’s Portsmouth Marine Terminal has welcomed the arrival of the first substation to be installed at the Coastal Virginia Offshore Wind (CVOW) project. The CS Wind Offshore and Semco ...